New precision line progress Facility preparation underway

New capabilities are on the way.

Follow the milestones, construction updates, and installation progress behind CSP's new precision processing line.

.040"–.312"Material thickness
25"–74"Coil widths
60,000 lbsMaximum coil weight
Q4 2026Target production launch

Project overview

A new line built for precision, flexibility, and future demand.

CSP is adding a new precision cut-to-length and stretcher-leveling line with in-line edge trimming. The investment is designed to support tighter flatness requirements, expanded processing options, and additional customer capacity.

The line will be supported by CSP's new Toledo facility at 5601 Enterprise Boulevard and is targeted to begin operation in Q4 2026.

Aerial drone view of Coil Steel Processing's Toledo facility

Basic information

New precision-line capabilities at a glance.

The confirmed processing range and project details from CSP's current expansion and line-card information.

Thickness

0.040"–0.312"

Widths

25"–74"

Coil Weight

Up to 60,000 lbs

Sheet Length

Up to 240"

Edge Trimming

0.250"–2" per side

New Facility

5601 Enterprise Blvd

Project timeline

From planning to production.

This timeline provides the project framework. Dates and progress media can be updated as construction and installation advance.

Complete

Project Announcement

New line and expanded capacity introduced.

Current Phase

Facility Preparation

Site and building work is underway for the new installation.

Upcoming

Equipment Delivery

Major line components arrive at the facility.

Upcoming

Install & Commission

Assembly, controls, testing, and team preparation.

Target

Production Launch

Targeted for Q4 2026.

Current phase: facility preparation. Project dates may shift as construction, equipment delivery, and commissioning progress. CSP will post verified updates here as milestones are completed.

Photos & video

See the project take shape.

Follow the project through updated photos and video.

New processing line equipment arriving on a trailer inside the CSP facility

First Delivery of the New Line

Blue processing line equipment unloaded inside the facility beneath the overhead crane

New Line Equipment Unloaded

Concrete walls and floor of the new equipment pit after the pour

Equipment Pit After the Concrete Pour

New line equipment on the delivery trailer with a worker preparing for unloading

Unloading the First Delivery

Crew working beside the new line equipment and overhead crane at the delivery trailer

Equipment Delivery Crew

Worker on a scissor lift working along the overhead steel structure

Overhead Work Continues

Crew working with concrete placement equipment at the new processing line pit

Concrete Pour at the Equipment Pit

Worker directing the concrete pump hose into forms at the equipment pit

Placing Concrete in the Pit

Concrete pump boom extended over the equipment pit inside the CSP facility

Concrete Pump in Action

Worker welding steel beside the equipment pit for the new processing line

Welding at the Equipment Pit

Worker welding a long section of steel pipe inside the CSP facility

Steel Pipe Welding

Steel pipes and construction forms inside the equipment pit

Equipment Pit Progress

Workers pouring concrete into the reinforced equipment pit for the new CSP processing line

Equipment Pit Concrete Pour

Concrete mixer truck delivering concrete into the new processing line foundation inside the CSP facility

Concrete Delivery for the New Line

Wide view of floor and foundation preparation for CSP's new processing line

Floor & Foundation Preparation

New concrete base poured in the processing line foundation area

Foundation Base Pour

Worker fabricating steel plate for the new processing line foundation

Steel Plate Fabrication

Steel supports installed around the equipment foundation pit

Equipment Pit Steel Supports

Concrete foundation formwork progressing inside the CSP expansion facility

Foundation Formwork Progress

Worker on a lift installing electrical railing for the overhead crane

Overhead Crane Electrical Railing

Rendering of the new CSP precision processing line

New Line Project Rendering

Interior facility preparation underway for CSP's new precision processing line

Facility Preparation

Excavator preparing the foundation area for CSP's new precision processing line

Foundation Excavation

Foundation excavation progress inside CSP's new Toledo facility

Excavation Progress

Concrete floor and utility trench preparation underway for CSP's new precision processing line

Site Preparation Progress

Workers installing reinforcing steel for the foundation of CSP's new precision processing line

Foundation Reinforcement Progress

Interior demolition underway to prepare CSP's Toledo facility for the new precision processing line

Interior Demolition Progress

Completed demolition of the small interior building at CSP's Toledo facility

Interior Building Demolition Complete

Start a conversation

Let's talk about your future processing needs.

Whether you are a current customer or exploring new processing options, CSP's sales team can help review your material requirements, timing, and future capacity needs.